Task Timeline

Task Timeline

TIME FOR TASK COMPLETION OF PROPOSALS

 

Note: Some of the tasks will be done simultaneously.

Peer review of proposed grant

2-3 weeks (review should begin well in advance of proposal development)
 

Develop budget and budget justification.

Modify SPH resources and environment template.

1-2 weeks

Collect biosketches and letters of support from supporters. 
 

2 weeks

Format text content. 
 

1-2 weeks

Organize data collection for complex tables. 
 

2-3 weeks

Scan http://www.uic.edu/sph/images from original sources. 
 

1-2 weeks

Prepare and submit PAF to Office of the Vice Chancellor for Research for approval (includes obtaining signatures)
 

4-5 days (1 day for signatures; UIC ORS requires 2 days for approval)

Assemble and send grant package to sponsor.

1-2 days 
 

 